Hydro-Québec, Chute-Allard Power plant

Location

Chute-Allard, LaTuque, Québec, Canada

Contract Value

35 000 000. $ CA

Duration

26 months

End of the work

December 2008

Chute-Allard hydroelectric power plant on "Upper St.Maurice river" comprising 6 "SAXO" type turbine-alternator groups for a total of 62 MW.

Detailed engineering, quality assurance, supply and installation of auxiliary service equipment, piping, electricity, T-A Control and HVAC as well as partial completion of architectural works.